World’s First Offshore Charging Solution for Zero-Emission Wind Ops

Prototype testing of the Ocean Charger charging the CSOV newbuilding Rem Power from an offshore wind turbine. (Image credit: Seaonics)
High-voltage charging tests were conducted in port to charge the batteries on the Rem Offshore-owned diesel-electric hybrid CSOV (Construction Service Operation Vessel) REM Power (built 2023) as well offshore from a charging point (cable reel, winch, and control system) mounted on a wind turbine.

“At 10 years old, the turbine is one of the smallest offshore, but the prototype proved it is possible to install the Ocean Charger on an existing turbine and charge an SOV from day one, using 11 kilovolt (KV) current delivering 6 MW of charge. Apart from a handful of improvement points to fix, the concept and control system are complete, and the product is available for sale as is. We’re first in the market and already in talks with wind farm owners,” said Bjørnar Huse, Sales Manager, Offshore Energy at Seaonics. He adds that because power current varies between wind parks and wind turbines, the commercial version will have to be customized for each project.

Significance and Benefits

The ability to charge vessels offshore in a cost-effective way is a central enabler for shipbuilders to deliver zero-emission SOVs to the offshore wind industry. “Connecting vessels to the power grid in the wind farm and charging batteries regularly is a big step towards increasing sustainable operations without using any additional energy sources. It saves the time and energy needed to return to port to charge, while the operating cost of electric SOVs versus diesel and alternative fuels is much lower because both the energy is cheaper and you reduce engine maintenance demands. You still need diesels for back-up power, but quite a lot smaller than for a full diesel operation, with lower Capex,” said Huse.

A large, 60-person SOV consumes 20 to 25 MW hours per day, so at 6 MW you can potentially charge for a full day’s operation in three to four hours. “But it’s better for the lifetime of the battery pack to never be completely depleted nor fully charged—between 50 and 80 percent is best. You could charge for six hours at night, say, then do ad-hoc charging during the day,” Huse said.

Meanwhile, wind farm owners are moving away from the idea of locating charging points on substations or expensive floating buoys. “The standard will most likely be to locate the charging point on a turbine. Downscaling the weight and cost also means you can have many charging points, reducing the need to cruise long distances to charge. The turbines are usually owned by the developer, so they can fit as many as required. It is easier mechanically to have charging points on a substation, but as these are usually owned by the grid owner, there is some doubt as to who would be responsible for their maintenance and insurance, etc. This will have to be sorted out project by project,” Huse added.

(Image credit: Seaonics)

Standardized Solution

The Ocean Charger’s standardized solution is cost effective because it uses an industry-standard connector plug and power levels both for offshore charging and in port. “The prototype worked using a standard vessel and crane. The plug is an industry-standard used for shore-charging cruise ships as well as Hoegh Autoliners’ Aurora-class hybrid-electric newbuild car carriers. Tying known technology together made it easier to get to a prototype in a relatively short time. We didn’t have to invent a lot of new components unlike some competitors using a bespoke plug,” Huse said.

The product can be fitted to any structure and vessel, and the power is integrated with the vessel switchboard and the chosen charging voltage. “The main development challenges were handling the medium/high current coming on board the vessel and navigating the relevant standards (IEC, ISO, etc.) for marine technical equipment. For example, there are a lot of class requirements on safety distance around the plug. Existing standards also mostly still cover shore-based equipment, so we had to make an offshore version of the different components,” Huse added.

The Current Issue

Discussions are currently underway with wind park owners regarding charging current. Wind parks usually have 66 or 132 KV, requiring one or two transformers—one on the charging point and another on the vessel—to get the high voltage down to medium or low voltage. “Some have asked us to explore bringing 132 KV, which is the standard current in big power lines on land, directly onto the vessel and do all the transformation onboard. However, managing such a high current would require a very bespoke handling and safety system. Feasibility depends on the cost of power integration and transformers,” said Huse.

“The cost-effective compromise is to stick with 11 KV, which is what the Aurora-class vessels use but is still high considering the standard shore connection for fishing vessels and small SOVs today is typically 690 or 1,000 volts, using the same equipment for both offshore and shore charging.”

Grabbing the Cable

The SOV approaches the charging point and uses a crane equipped with a gripper that ‘grabs’ the end of the cable and pulls it onto the connection area integrated on the vessel deck. The REM Power has a fully 3D compensated crane and can connect even in rough weather, but smaller SOVs and maintenance craft that don’t have a crane can use the motion-compensated gangway instead. “High accuracy isn’t necessary, as the automated handling system guides the plug to the right place, eliminating any need for manual operation,” said Huse.

The vessel must be on DP during charging but with a larger footprint to reduce power consumption. The cable is slack, so the vessel can move 20 meters or so back and forth without damaging anything. “The DP safety system will kick in if the vessel loses position or, if necessary, the control system will automatically release the cable in an orderly manner. The system has been designed with two levels of redundancy for emergency release,” Huse said.

(Image credit: Seaonics)

“It is of course possible the plug may occasionally be released in a non-orderly manner and be submerged, leading to water intrusion both in the plug and cable. That may require the whole cable to be replaced involving time and cost. No industry standard plugs have been approved or are capable of being submerged, so we had to design a watertight cover. The handling system opens the cover when the plug is on board and guides it into the charging notch, and in reverse when charging is complete.”

Time for Tailoring

Huse says it would take a few months to customize the configuration and get approvals for a specific wind park and vessel. “For wind farms that will be installed in two to four years’ time, there is ample time to do final integration design, fabrication, and installation on a new chartered SOV or retrofit an existing one. Fitting the charging points to turbines before they are installed also streamlines the operation.”

Seaonics can write an offer today for the Ocean Charger in its current configuration. “We know exactly how much the vessel integration will cost, and how much the charging point on a turbine will cost. Total project cost will obviously vary depending on how many charging points it entails, and customization required to match the owner’s operating parameters.”

The Ocean Charger was developed by a consortium led by Ålesund-based Vard Design and sister companies Seaonics and Vard Electro, alongside partners Rem Offshore, Solstad Offshore, SINTEF Energi, SINTEF Ocean, DigiCat, Sustainable Energy, Equinor, Source Galileo Norge, Corvus Energy, Plug, Shoreline, Sustainable Energy, University of Bergen, Norce and Maritime CleanTech. “Coming up with a pioneering product at speed demonstrates what great partners with different expertise can achieve in collaboration—which is the only way to accelerate sustainability in our industry,” Huse concluded.

Latest Issue:

Today, no frontier is beyond an offshore operator’s capacity. While Remote Marine Operations can mean different things to different ocean…

Your cON&Tent matters. Make it count.

Send us your latest corporate news, blogs or press releases.

Search