Seven of the eight sections of the Onshore Pipeline have been successfully hydrotested. Sable will complete the final hydrotest in order to meet the final operational condition to restart the Onshore Pipeline as outlined in the Consent Decree. Sable expects to fill the ~540,000 barrels of crude oil storage capacity at LFC by the middle of June 2025 and subsequently recommence oil sales in July 2025.
Production Restart
On May 15, 2025, Sable initiated the flow of oil production from six wells on Platform Harmony of the SYU to LFC at a rate of ~6,000 barrels of oil per day.
Sable has been testing wells on Platform Harmony throughout May 2025, and the well tests have performed consistently stronger than they did at the time of shut-in on May 19, 2015, when the SYU produced approximately 45,000 barrels of oil equivalent per day.
As of May 18, 2025, approximately 30% of the 32 producing wells at Platform Harmony had been tested, and the remaining wells are projected to be tested over the next several days.
Sable expects to initiate production from the additional 44 wells on Platform Heritage and the additional 26 wells on Platform Hondo in July 2025 and August 2025, respectively.
“SOC is proud to have safely and responsibly achieved first production at the Santa Ynez Unit,” said Jim Flores, Chairman and Chief Executive Officer. He continued, “The impressive well tests from Platform Harmony confirm the prolific nature of the Santa Ynez Unit reservoir after being dormant for ten years. SOC is excited about our development plan and prospects for the future. This milestone achievement is a result of a tremendous amount of effort from all of Sable’s employees, contractors, Board of Directors, stakeholders, and suppliers. We are very grateful for the cooperation and partnership from our local community and regulatory bodies as we seek to provide energy security to the State of California.”