Framo Technology Used to Successfully Install Wind Turbine Foundations

A total of 60 suction buckets have been pumped in place as foundation for the 20 wind turbines in Ørsted's new wind farm Borkum Riffgrund 2.

In June 2018, a team of specialists from Framo, the Norwegian Geotechnical Institute (NGI) and GeoSea installed the first of the 20 suction bucket jackets at the offshore wind farm. After periods of storm and high waves, the foundations of all 20 wind turbines were safely pumped into the seabed with the final jacket foundation installed on Monday, 30 July. The full commissioning of the wind farm is planned for early 2019.

Framo“It’s a milestone for Framo. This is the first time our technology has been used to pump so many wind turbines in the same wind farm and is quite unique that so many wind turbines are anchored with suction anchors in one field.” says Jørgen Brandt Theodorsen, Area Sales Manager Framo.

“The suction bucket jacket technology for offshore wind farms has gone from concept to reality during the last five years. Besides lowering costs due to the increased installation speeds compared to traditionally piled jackets, the concept provides for easier decommissioning and practically noise free installation.” says Thomas Langford, Director for Offshore Energy at NGI.

Framo is a sub-contractor to NGI in the installation of the 20 offshore wind turbines. NGI and Framo have collaborated on the installation of offshore anchoring and foundation elements using suction/vacuum since the 1990s.The technology of suction and bucket foundation has been used to secure and safely anchor platforms and offshore installations around the world. Now larger wind farms are being built with this technology. The foundation is installed by pumping water out of the buckets. This creates a suction/vacuum, which press the buckets into the seabed.

The windfarm Borkum Riffgrund 2 is located 54 kilometers off the coast of Lower Saxony, in the German North Sea. In the installation of the 56 wind turbines, 20 will use the suction bucket technology as foundation and 36 will be supported using monopiles. The three-legged foundations measure more than 50 meters in height and weighing 950 tons each.

“Compared with installing monopiles, suction anchor technology has a more environmentally friendly footprint. When pumped in place, the fish does not scare away during the installation process due to noise and it is easy to reverse the operation.” says Theodorsen.

When the 8,5 megawatt giant turimages, are in place, they rise 109 meters above sea level and have a wing span of 164 meters.

Theodorsen believes several companies will pump the anchoring into place.

“An increasing number of companies invest in offshore wind to meet the future demand for energy, as well as to offer a more environmentally friendly energy alternative. It is a growing market where we are proactive to take part in this development. The Ørsted project opens up a new market for us in major wind farm developments and is an alternative to traditional installation methods.” concludes Theodorsen.

Latest Issue:

The ocean sector is fully immersed in a fundamental paradigm shift, with advances in Uncrewed Vehicles & Marine Robotics giving…

Your cON&Tent matters. Make it count.

Send us your latest corporate news, blogs or press releases.

Search