Baltyk 2 and Baltyk 3, developed by Equinor and Polenergia, will be among Poland’s first operational offshore wind farms. Together, they will generate enough renewable energy to power more than 2 million households, marking a significant step forward in Poland’s energy transition and energy security.
To bring this green energy ashore, Jan De Nul is working closely with its partner Hellenic Cables, responsible for the design and manufacturing of the subsea export cables.
From Route Preparation to Cable Protection
Jan De Nul’s work on Baltyk 2, located 37 kilometers off the Polish coast, began in 2025 with the clearance of boulders along the cable routes, ensuring safe installation conditions. In June this year, the cable-laying vessel Isaac Newton started installing 120 kilometers of export cables along the prepared routes. The team completed the installation campaign by pulling in the cables to the offshore substation, preparing the connection of the wind farm to the Polish electricity grid.
To complete the works, the vessel Symphony and trencher Swordfish trenched the cables wherever possible, burying them beneath the seabed for long-term protection against external impacts.
Looking Ahead to Baltyk 3
In 2027, Jan De Nul will return to Poland to connect the neighboring Baltyk 3 offshore wind farm to the mainland.